AirTrunk JHB1
AirTrunk (Blackstone)
Operating ยท Colocation
Grid power210 MW
IT load150 MW
Blackwell-equiv.90k
Reported figure: 150 MW as IT / critical load. Converted with PUE 1.40 (colocation campus default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).
| Location | ๐ฒ๐พ Johor, Malaysia |
|---|---|
| Region | Asia Pacific |
| Notes | 150 MW; opened 2024 |
| Last checked | 2026-11-21 |
Sources
Nearby in Malaysia
| Facility | Location | Grid power |
|---|---|---|
| Princeton Digital JH1 | Johor | โ |
| Equinix JH1 | Johor | โ |
| Yondr Johor | Johor | 420 MW |
| Bridge DC Johor | Johor | โ |
| DayOne Nusajaya | Iskandar Puteri, Johor | 662 MW |
| YTL Green Data Center Park | Kulai, Johor | 1.20 GW |