Microsoft Fairwater Atlanta
Microsoft
Operating · Hyperscaler · AI-focused
Grid power763 MW
IT load636 MW
Live IT today (est.)636 MW
Blackwell-equiv.382k
Reported figure: 636 MW as IT / critical load. Converted with PUE 1.20 (hyperscale data center default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).
| Location | 🇺🇸 Fayetteville, GA, United States |
|---|---|
| Region | North America |
| Notes | Built by QTS; Epoch est. 636 MW IT, GB200; Fairwater site #2 (Oct 2025) |
| Last checked | 2026-11-21 |
Sources
Epoch AI — Microsoft Fairwater Atlantahttps://epoch.ai/data/ai-data-centers/directory/microsoft-fairwater-atlantaMicrosoft — Azure AI superfactoryhttps://blogs.microsoft.com/blog/2025/11/12/infinite-scale-the-architecture-behind-the-azure-ai-superfactory/
Nearby in United States
| Facility | Location | Grid power |
|---|---|---|
| QTS Atlanta Fayetteville | Fayetteville, GA | — |
| Applied Digital Delta Forge 2 | Brookwood, AL | 262 MW |
| Meta Forest City | Forest City, NC | — |
| Google Lenoir | Lenoir, NC | — |
| TeraWulf Kentucky campus (Anthropic lease) | Kentucky | — |
| AWS Madison County | Canton, MS | 1.20 GW |