Applied Digital Polaris Forge 1
Applied Digital · CoreWeave
Operating · AI campus · AI-focused
Grid power500 MW
IT load400 MW
Live IT today (est.)250 MW
Blackwell-equiv.240k
Reported figure: 400 MW as IT / critical load. Converted with PUE 1.25 (AI campus default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).
| Location | 🇺🇸 Ellendale, ND, United States |
|---|---|
| Region | North America |
| Notes | 400 MW leased to CoreWeave; ~250 MW operational after Building 2 phase 2 (Oct 2026) |
| Last checked | 2026-11-21 |
Sources
Epoch AI — CoreWeave Ellendale NDhttps://epoch.ai/data/ai-data-centers/directory/coreweave-ellendale-ndConverge Digest — 75 MW phase onlinehttps://convergedigest.com/?p=112622Baxtel — Building 2 phase 2 (Oct 2026)https://baxtel.com/news/data-centers/ntt-amsterdam-1?page=6
Nearby in United States
| Facility | Location | Grid power |
|---|---|---|
| Applied Digital Polaris Forge 2 | Harwood, ND | 350 MW |
| Google Council Bluffs | Council Bluffs, IA | 284 MW |
| CyrusOne Council Bluffs | Council Bluffs, IA | — |
| Google Pine Island | Pine Island, MN | — |
| Microsoft West Des Moines | West Des Moines, IA | — |
| Meta Altoona | Altoona, IA | — |